Endeavour Silver Q4 2023 Earnings Call Transcript

There are 9 speakers on the call.

Operator

Thank you for standing by. This is the conference operator. Welcome to the Endeavour Silver Corp. Full Year 2023 Financial Results Conference Call. As a reminder, all participants are in listen only mode and the conference is being recorded.

Operator

After the presentation, there will be an opportunity to ask questions. I would now like to turn the conference over to Galina Melacher, Vice President of Investor Relations. Please go ahead.

Speaker 1

Thank you, operator, and good day, everyone. Before we get started, I ask that you view our MD and A precautionary language regarding forward looking statements and risk factors pertaining to these statements. Our MD and A and financial statements are available on our website at www.edrsilver.com. With us on today's call is Dan Dickson, Endeavour Silver's CEO as well as Elizabeth Fenner, our Chief Financial Officer and Don Gray, Endeavour's COO. Following Dan's remarks, we will then open up the call for questions.

Speaker 1

And now, over to Dan.

Speaker 2

Thank you, Galena, and welcome, everyone. As we commence this year's earnings call, I think it's important to acknowledge the dynamic landscape that shaped the mining sector in 2023. Roller coaster market forces led to volatile and lower equity prices. These events negatively impacted company valuations across the precious metals sector, creating a significant disconnect from the underlying commodity prices. With this broad market backdrop, we navigated higher operating costs, adding complexity to our operations.

Speaker 2

This theme was apparent for all Mexican mining firms, which saw cost pressures across multiple channels. To put this into perspective, I'll provide some key data points. Over the last 3 years, the Mexican Consumer Price Index surged by more than 21% and was amplified within our industry as key inputs such as steel, reagents and other consumables were impacted by supply constraints. Furthermore, from Q4 2021 to Q4 of 2023, the Mexican peso strengthened by nearly 20% against the U. S.

Speaker 2

Dollar, had cascading effects on our in country purchases and labor costs. As I look back on the year, I can affirm that our operations team displayed unwavering dedication in navigating these challenges. Today, I don't want to just reflect on these challenges, but to emphasize the strategic initiatives we've implemented to ensure the growth and success of our company. On a consolidated basis this year, we produced 8,700,000 silver ounces equivalent metal, which met guidance after 2 consecutive years of exceeding production guidance. Production was near the lower end of the guidance range with a production shortfall in Q3, largely due to mine resequencing changes we implemented to improve ventilation and ultimately worker safety.

Speaker 2

This temporary in operations results in a reduced mine output and ore grades. I am pleased to say Guanacevi's performance improved significantly in the 4th quarter as the planned improvements were executed extremely well and swiftly. Not only did Guanacevi's production return to historical levels, but our recovery strategy more than met expectations as silver grades, gold grades and plant throughput exceeded our estimates. The plant refurbishments completed at the beginning of Q4 enhanced our operational flexibility to exceed the historical throughput of 1200 tonnes per day. These improvements and enhancements led to escalated costs in the second half.

Speaker 2

However, cost metrics significantly improved in Q4. While Guanacevi had its challenges in Q3, Bolanito's performance remained steady with increased silver production offset by lower gold production in the Q4. From a financial standpoint, for the year, we reported revenue of $206,000,000 with cost of sales of $169,000,000 for operating earnings of $37,000,000 and mine operating cash flow of $40,000,000 After exploration, G and A and other investment expenses, we reported a net income of $6,000,000 or $0.03 per share. For the year, Guanacevi delivered $14,300,000 of mine free cash flow and Balamidos delivered $2,500,000 Our cost of sales increased 6% compared to the previous year. While there are a number of drivers, a strong Mexican peso and inflationary pressures on consumables were the 2 most impactful.

Speaker 2

Again, these two factors with lower than planned ore grades in mine and ore grades mined due to the mine resequencing in Q3 contributed into elevated cost metrics for the year with cash costs and all in sustaining costs at $13.49 $22.93 per ounce respectively. Both metrics were higher than we originally guided. However, the Q4 gave us some footing as costs came down significantly from Q3. Our 4th quarter cash costs and all in sustaining costs were $12.54 $21.48 per ounce respectively. The remediation efforts extended into early Q4 and the positive momentum on these initiatives are expected to carry forward.

Speaker 2

Looking to 2024, containing costs and finding efficiencies will remain in focus. While we continue to experience inflationary pressures and strong local currency, we are aggressively implementing business improvement initiatives to mitigate these headwinds. As of year end, we had cash of $35,000,000 and working capital of $43,000,000 Cash decreased in Q4 as funds were spent on the development activities at Terronera and long term prepaids went up significantly as we placed deposits with contractors and equipment. Working capital has fallen as we continue to invest in the Terronera project. With this investment, we've built up our non current assets, including $22,000,000 in construction deposits related to the Terronera build and $23,000,000 in value added tax.

Speaker 2

The EBITDA receivable has been submitted for processing and the company is working with authorities on timely collection. However, we conservatively classify these as non current assets until collection starts. As per requirements under the $120,000,000 senior secured debt facility, we must primarily self fund development through cash on hand before drawing on the facility. As such, we are well positioned to satisfy the financing requirements of the project and are expecting to complete our first draw in March. During Q4, we raised gross proceeds of $39,000,000 through the ATM and another $24,000,000 was raised subsequent to year end to ensure there is sufficient funding in place for the development of Terronera.

Speaker 2

When you add this all up, we have sufficient capital. We're confident that the actions we've taken will see Terronera through the finish line, while also supporting the high value organic growth initiatives in place at Pitria. As a reminder, Pitria is our next project in the pipeline located in the Durango State of Mexico. It's one of the world's largest undeveloped silver deposits with nearly 600,000,000 ounces of silver defined. Let's give a quick update on the construction progress at Terronera.

Speaker 2

In January 2024, we completed a risk analysis on the project for the remaining expenditure and provide an updated initial capital cost and execution plan. Marrying the trends we experienced at our producing mines in Mexico, we faced similar headwinds at Terronera during the construction year. The impacts of a stronger Mexican peso, ongoing inflation and tight markets for equipment and bulk materials all contributed to an 18% increase to our updated initial capital estimate of $271,000,000 up from $230,000,000 Capital pressures notwithstanding, the pace of the project development continues to advance and is on track with previous guidance with commissioning planned in Q4 of 2024. At the end of the year, we reached 46% completion on the overall project progress compared to the original guidance. However, due to the adjusted weighting on the updated initial CapEx, management estimates an adjusted 43% completion as of December 31.

Speaker 2

We had spent $122,000,000 on direct development, while project commitments totaled $171,000,000 or 63% of the updated capital budget. During Q4, we concentrated our efforts on completing key items, including earthworks for our upper mill platform, procurement of equipment and advances in plant concrete and achieved significant progress in constructing our process plant. If you are interested in seeing photos of the construction progress, I encourage you to visit our website under the Terronera page. Let me provide a few recent highlights of progress at Terronera, which demonstrates our strong commitment to responsible, sustainable development and working collaboratively with our local key stakeholders. Starting with safety, our Takeda culture has served as a solid foundation for building a strong safety record at the project.

Speaker 2

We finished the year with no lost time accidents over 172 days of work at site, which translates to about 600,000 man hours. Specifically, we heightened safety protocols significantly, especially during the rainy season and notably in Q4 when we were alerted to the imminent arrival of Hurricane Lydia along the coastline. Despite facing a Category 4 storm, our site weathered the event admirably, experienced only minor damage to exterior fixtures and some fallen trees. The robustness of our drainage system proved crucial in maintaining the integrity of the site and roads. As a precautionary measure, we suspended on-site activities to ensure the safety of our personnel.

Speaker 2

Fortunately, power and normal operations were swiftly restored within a few days. We also supported local relief efforts with our on-site team helping local communities to recover. Over the year, we've emphasized the importance of the efficiency of our mine development. To address this, we strategically onboard a top tier talent and successfully transitioned to our in house mining team after startup with mine contractors. This shift was always designed and has yielded significant development efficiencies with notable enhancements in Q4 where we met our daily advance rate targets facilitated by improved blasting techniques, water control and better ground conditions.

Speaker 2

As the year concluded, our cumulative underground development reached over 2,200 meters, marking a substantial 70% increase in meters compared to Q3. The positive momentum in advance rates indicates a promising trajectory forward. During the quarter, Portal 4 Incline broke through the surface and preparations are now underway to complete the portal structure in Q1, 2024. The majority of construction activities have progressed well at the plant site. Currently, surface construction stands at nearly 50% completion and the advanced stage of concrete works sets the stage for commencement of vertical construction, which started in January.

Speaker 2

At year end, the concrete was nearly done in both the grinding and the flotation areas and was being prepared for the general contractor begin structural steel and mechanical installations. Also during Q4, we initiated the construction of the access road connecting lower platform to the tailing storage facility area and the upper mill platform. Our Terronera workforce continues to grow with over 520 employees and contractors on-site. On the procurement side, all major equipment was ordered by year end and the team is focused on procuring bulk materials, including structural steel piping and electrical cable. And lastly, on the communities relations side, we continue to have full support from the municipality and continue to engage and educate the municipality as we progress at site.

Speaker 2

Okay. So I've touched a lot on 2023. Let's have a look at what's at store this year for Endeavor. We enter 2024 in a solid position both financially and operationally with a number of strategic initiatives underway that will drive our future growth. Our production outlook anticipates gold and silver to be consistent with 2023 and managing costs will continue to be a key focus as we aim to offset the impact of rising costs.

Speaker 2

Guanacevi and Baleniz are mature assets and we have plans to invest more than $30,000,000 in sustaining capital to optimize their performance and maximize output. Equally important on this year's agenda is advancing our growth profile. We have $9,000,000 earmarked across our exploration portfolio to continue our long successful track record of growing through the drill bit. For instance, at Pithoria, we hope to invest over $5,000,000 on several initiatives. This year's plan is to conduct a 6,000 meter drill campaign to target the high grade zones and feeder structures of the existing resource.

Speaker 2

We'll use the data collected to guide our next steps with the expectation to assess this project as an underground silver mine. Ultimately, the combination of Terronera and Pitria supports our long term vision to become a 20,000,000 ounce senior silver producer and provides a value proposition that is best in the silver space. With the constructive macro backdrop for both gold and silver in place, we believe our growth strategy is well timed and well suited to drive outperformance for our stockholders in the coming years. I'd like to add that over the past few years, we have deliberately reinvested in the business for long term growth. Now with less than a year to go before Tarrinah comes on stream, we can expect to see the benefits of these investments accrue to our shareholders.

Speaker 2

2024 is about execution at Terronera, which is clearly transformational. Upon completion, we expect Terronera will nearly double our production, significantly reduce our cost profile and provide substantial free cash flow for our shareholders. It's going to be exciting year for Endeavor and our stakeholders. While we face a few more capital intensive months ahead as we ramp up to production, we look forward to the arrival of strong free cash flow generated in 2025. Before opening for questions, I'd like to formally welcome Elizabeth Cenas, our recently appointed CFO to our executive leadership team.

Speaker 2

Libby joined us in January and we're thrilled to have her on our team as a finance executive with a predominantly Latin American focus. She brings over 20 years of value in accounting, corporate finance and corporate treasury to her role. On behalf of the entire team in Andeavor Silver, I would like to also thank Christine West, our former CFO, for her many contributions to the company over the past 16 years. Throughout her career with Endeavour, she has demonstrated incredible dedication to work and to the success of our company. Christine, we wish you all the best in retirement.

Speaker 2

Together with the other members of our management team, we'd be happy to take your questions. Let's open up the lines, operator.

Operator

The first question comes from Jake Sekelsky with Alliance Global Partners. Please go ahead.

Speaker 3

So just starting with ASIC guidance for the year, can you speak to or maybe quantify the positive impact that the recent move in the gold price might have from a gold credit perspective?

Speaker 2

Yes. Well, for the year, just for all the listeners, we'll produce about 5,000,000 ounces of silver and about 35,000 ounces of gold. Obviously, a $100 impact on increase in the price of gold has a significant impact from a byproduct standpoint. We did our budgeting, I believe, at $18.40 for the year on gold. Obviously, today, we're sitting around just shy of $2,200 That impact, well, first of all, significantly drives down on a per ounce basis, by product basis.

Speaker 2

Specifically, when it goes right into our cash costs and where our guidance was, it's beneficial, but I think it's still early days and we'll stick by our guidance of using $18.40

Speaker 3

Okay, that's helpful. And then just at Ceroneira, you just touch on the remaining exposure from a CapEx standpoint to broader inflationary pressures and what else still makes you lock in then?

Speaker 2

Yes, I think at this point, Jake, the inflationary pressures is probably taken away just the fact that we've done most of our key procurement even on bulk items now. When we re estimated the price of Terronera, the initial CapEx going from $2.30 to $2.70 we adjusted our Mexican FX rate to 17.3 percent in our budget. And so as long as the Mexican FX rate stays there, I think we'll be all right. Now it just comes down to productivity at site and making sure we execute. Again, there's always going to be small headwinds, whether it's inflationary or if the peso continues to depreciate.

Speaker 2

But the impact on what's left to build over the next kind of 9 months is small as long as we produce.

Operator

The next question comes from Heiko Ihle with H. C. Wainwright. Please go ahead.

Speaker 2

Hey, Heiko. Hopefully, your question comes through. You sound a little digitized at this time. Apologies Heiko from our end, we couldn't get what you're saying. Everything's come through digitized.

Speaker 2

Operator, if we can maybe go to the next question and put Heiko back in queue, if possible.

Operator

Certainly. The next question comes from Lucas Pipes with B. Riley Securities. Please go ahead.

Speaker 4

Thank you very much, operator. Good morning, everyone.

Speaker 2

Good morning, Lucas.

Speaker 4

I'll try not to sound like R2D2, but first I wanted to add my congrats to Elizabeth and then Christine, I hope you enjoy retirement. Dan, maybe a first question on the cost side. What else can be done? What else are you looking at to mitigate costs kind of going forward? Would appreciate your thoughts.

Speaker 4

Thank you.

Speaker 2

Yes. Guanacevi, it comes still we still have opportunity for productivity. So in Q3, we had ventilation issues that made it extremely warm for our employees to work underground. And as we got deeper into the El Curso area, it got hotter. And Q4 or Q3 and Q4, we put through a new ventilation system and ultimately increased our pumping of the water that was coming out.

Speaker 2

And we got a lot of benefit of that in Q4, but there is still some benefit to come in Q1 and that just comes down to productivity. So when the mine got overly hard, we had to give more breaks to our employees and put them in cooling chambers to effectively make sure that they're operating in a safe manner. And I think at this point in time with the ventilation and where the temperature is underground, they can work fully. And so there's productivity gains that could be gained at Guanacevi. And then it's working across both Bolanos and Guanacevi and making sure we're procuring and going out to a number of different vendors and trying to get some bulk work done on that.

Speaker 2

And there's always abilities to kind of look at what we're doing from a purchasing standpoint, what we're doing from a productivity standpoint, making sure that ultimately our mine development is a big focus this year that we are getting our advance rate as expected and putting some incentives to make sure that we're doing that as a group. So there's a lot of little things that we can do. Obviously, they're mature assets that go on and see in Volumes and there's kind of diminishing returns over the years. But I think with what we've seen in Mexico with regards to all those cost pressures that we have to look at anything that's available to us to try to reduce our costs on a

Speaker 4

per ton basis. And switching over to Terronera, where does the workforce stand today and what's kind of your employee count versus contractor labor. I think you've mentioned that as kind of a key driver of productivity and efficiency going forward? And then in terms of the ball mill, has that been transported to the plant yet? Or is that expected in Q1?

Speaker 2

Yes. No, for sure. To answer the first question, so at December 31, we had five 20 total employees and contractors. Of that 520, about 120 were direct employees. Through this year, we do expect to peak around 700 on-site.

Speaker 2

And then with regards to our ball mill, it's a good question. I mean, I touched a lot on Q4 and what was happening at site. Our SAG mill and our ball mill are actually already at site and they have been placed. So it's been exciting kind of Q1, but we'll have a full update of Q1 generally in April from a construction standpoint.

Speaker 4

All right. Well, I really appreciate it. I'll turn it over. Best of luck.

Speaker 2

Thanks, Lucas.

Operator

The next question comes from Steven Sook with Stifel. Please go ahead.

Speaker 5

Hi, Dan and team. Congrats on a good quarter. My question is just more on Terronera and the underground rates. I think this was kind of a critical path item and great to hear they've come up so notably over the last quarter, can you just comment on if those are tracking to your original plan or is there catch up to do there or are you seeing additional efficiencies that you hadn't counted on at this point in the transition? And just a little more color around how that's progressing?

Speaker 5

Thanks.

Speaker 2

Yes, it's a very good question, Stephen. And our plan ultimately is about 4 meters of advance per critical heading per day. We were able to achieve that in Q4, and we've seen that in Q1. There's always a little bit of opportunity with the redesigning of our mine plan. We continually redesign our mine plan.

Speaker 2

I'd almost call it dynamic just based on ground conditions, water flow, a number of things that we've done. We've got a very seasoned team on-site and they've been phenomenal, I would say, over the last 6 months. So we are hitting our advance rate as planned to make sure we're in commissioning for Q4 of this year.

Speaker 5

Perfect. Great to hear. No, that's it for me. Appreciate it.

Speaker 2

Thanks, Stephen.

Operator

The next question comes from Craig Hutchison with TD Securities. Please go ahead.

Speaker 6

Hi, good morning guys. Thanks for taking my question. Good morning. Good morning, Dan. Maybe a similar question to Stephen is just with regards to critical items.

Speaker 6

You guys mentioned the tailing storage facilities on the critical path. Any updates on kind of where that stands? And you did mention that you're going to provide an update in Q1, but any kind of numbers you can kind of give us in terms of where the overall project sits here in mid March, 43% at year end, kind of where are you in the 50s now? And anything on that would be helpful. Thanks.

Speaker 2

Yes, you're correct. And maybe to kind of expand on Steven's question, right now we see the critical path being mine development and the tailings storage facility and probably the tailings storage facility originally on the outside of the build wasn't expected to be a critical path item, but just on timing of when we got started on that lower platform and where the tailings dam is. It's right there with mine development. I'm happy to say that in Q1, all our work's begun on the TSF, with the expectation that that work will be done mid year. So there's still some time around it.

Speaker 2

Again, productivity around the TSF starts off a little bit slow, but it's picked up. And hopefully we can make it so it's no longer a critical path item and it remains to be the mine development.

Speaker 6

Okay. And just overall progress, any updates from the sort of 43% year end? Yes.

Speaker 2

Like I say, we originally thought 46% and we adjusted it to the updated initial CapEx. And right now at December 31, we felt we were about 43%. Generally, we're adding 2% to 3% of efficiencies per month and that's generally the plan. So we're probably sitting at the beginning of March, not mid March here, but around 50%. I know Don Gray is on our line, our COO.

Speaker 2

Don, would you have any other color you'd like to add to that?

Speaker 7

Yes. Thanks, Dan. So Craig, we're just under 50% and we'll have a lot better visibility on that at the end of March. But things are moving really well at site. A lot of work going on, on the mechanical and the upper platform.

Speaker 7

Like Dan said, we've set the mills and also starting to set pumps and flotation cells and things like that. So and the excavation is going well down on the lower platform area.

Speaker 6

Okay, great. Maybe one last question for me. Just you guys are planning to draw down the debt facility this quarter. Is that still on track? Will it be the full amount or will it be sort of increments of the full amount?

Speaker 1

I'll take that one. This is Libby Senna. We are planning to draw down the 1st draw this month, but not the full amount.

Speaker 6

Okay.

Operator

The next question comes from Heiko Ihle with H. C. Wainwright. Please go ahead.

Speaker 8

Can you guys hear me okay?

Speaker 2

You sound phenomenal, Heiko.

Speaker 8

I'm in my house. I don't know what happened earlier. And so I hung up and dialed back in. So if this question was asked, my apologies in advance. Dan, earlier on this call in your prepared remarks, you mentioned early Q4 for commissioning.

Speaker 8

Reading into this, we're looking probably at October or maybe early November, so 7 months away. Has that timeline changed at all? And I just went through the February 12 press release and it also just states Q4. I mean, we probably had more like mid Q4 in our model and this obviously quite a bit better. And if this timeline has changed, what exactly helped move it forward, please?

Speaker 2

Heiko, we've always publicly said that we're Q4 commissioning, and we've never indicated whether that was going to be October, November, December. And I think that buys a little bit of time. We initially had planned in our feasibility study kind of a 3 to 6 month commissioning phase. And in our model right now, maybe it's a little bit shorter than the 6 months and closer to that 3 months. But the expectation at the outset since April 2023 till today is we've publicly been saying it's a Q4 commissioning for 2024.

Speaker 8

Got it. Okay. Building on that, and I'm just thinking out loud here, the cost curve for Perionero obviously has sort of ramp up associated with it. In your internal model, has anything with this ramp up curve changed compared to where you maybe were a year or 2 ago before it really started getting fully built?

Speaker 2

Maybe I'm not fully understanding your question. So with the ramp up of the initial CapEx going from $230,000,000 to $270,000,000 you're asking about the impact on our model?

Speaker 8

No, no. Once it's actually in production later this year, with I assume as efficiencies of type get added within 2, 3, 4 quarters as the whole thing ramps up, anything you're seeing, anything that changed internally over the past couple of months and what you're seeing in the costs for the ramp up?

Speaker 2

Yes, to be honest, the cost per ounce? Yes. We haven't come out publicly and from an internal standpoint on operating costs. So clearly, from our existing operations, we've seen operating cost pressures increase because of the Mexican peso, because of the inflation rate. Publicly, in our feasibility study, we put out an $87 cost per tonne on the operation.

Speaker 2

Again, that was at the 17.50 tonne per day. When we announced the construction decision for Terronera, we talked about the 2,000 ton per day scenario, which brought our cost per ton down to 80 dollars Now clearly, with the pressures that we've seen across the space, that $80 per ton is probably not going to be $80 per ton increase in steel prices, increase in reagents is going to push that up. We haven't remodeled all that. As we approach operations and going into commercial production, we'll probably update the market at that time with regards to those. But just knowing the operations and where those pressures have been, I don't think it will be significant or change the outcome of what we do at Terronera.

Speaker 8

Perfect. Now that's fair.

Operator

This concludes the question and answer session. I would like to turn the conference back over to Dan Dickson for any closing remarks.

Speaker 2

Well, thanks, operator, and thanks to everybody attending this year's 2023 earnings call. Hopefully, 2024 turns out to be a wonderful year. I know in the last 2 weeks, we've had a real push on gold prices, and hopefully that translates into the silver price. I know we're still sitting close to 90:one ratio and ultimately we see some love in the gold price that will translate over to the silver price. It's our job to execute this year on Taranera, and I think we'll have a very wonderful 2024 and hopefully beyond that.

Speaker 2

Thank you, and have a good day.